Ordered pipes, and called Miss Utility to mark underground utilities |
![]() |
We had to remove some tree branches to make room for the drill rig |
![]() |
Chipper eats pine tree branches |
![]() |
Drill rig is ready |
![]() |
A few more branches will be trimmed |
![]() |
Drainage ditch and water containment pool |
![]() |
The start of drilling for the 1st hole, we hit rock at 30 feet |
![]() |
Pushing geothermal pipes down the hole |
![]() |
Adding grout |
![]() |
Filling grout into the grouting machine |
![]() |
The type of grout used CLICK for more information |
![]() |
Hole number 1 was completed at the end of the first day |
![]() |
The next day hole 2, we hit water at 70 feet with 30 GPM rate |
![]() |
Measuring the containment pool |
![]() |
Pump truck removes the water |
![]() |
Grouting hole number 2 |
![]() |
After drainage, filling up the containment hole and trench |
![]() |
Both holes are completed at day 2, waiting on trench to the house |
![]() |
Foster Well & Pump Company CLICK for more information |
![]() |
Trench open and geothermal pipes are being tied in to the header |
![]() |
Trench is about 30 feet long |
![]() |
Pipes will connect and enter the house under the foundation |
![]() |
Some Dow Blue Board covers the wells for good measure and trench is covered |
![]() |
Outside Loop Installation is Finished!! |